Signage Improvement Works

Advertising consent has been obtained for new signage to be installed at Gate 1 to the estate.  The new signs will be installed to the left and in front of the gatehouse. 

The approximate timetable of works are as follows;

  • Removal of existing signage and installation of temporary signage has taken place
  • Mound removal and temporary works to soil areas early July
  • Foundations for new signage will be poured last week of July
  • Erection of sign frame and granite on the 19th and 20th August (Saturday/Sunday)
  • Remedial landscaping works to be carried out during September

We are sorry for any inconvenience these improvement works may cause.  Temporary gate closures may be in place during this time, with traffic diversion measures (Saturdays only to minimise disruption). 

Security will be on hand to assist with traffic diversion.